International

Kudankulam nuke plant ‘to begin power output soon’

Kudankulam nuke plant ‘to begin power output soon’

July 14, 2013 | 09:30 PM

Agencies/Chennai

India’s 21st nuclear reactor at Kudankulam in Tamil Nadu is functioning well after it began nuclear fission process for the first time Saturday night, a senior official said yesterday.

“Everything is progressing in a normal manner. The reactor is functioning well as per expectations,” R S Sundar, site director of the Kudankulam Nuclear Power Project (KNPP), said.

“If all goes well, we will be able to connect the plant to the southern grid in 30-45 days,” he added.

The first unit at KNPP attained criticality at 11.05pm Saturday. All its parameters remained normal. This is a much-awaited development for the Indian nuclear establishment.

Sundar said sustained nuclear reaction had been achieved and all parameters were as per expectations.

“After a long time, the mood here is good,” he said.

Top officials of the Indian nuclear establishment, including R K Sinha, chairman of the Atomic Energy Commission (AEC) and secretary of the department of atomic energy (DAE), and K C Purohit, chairman and managing director of the Nuclear Power Corporation of India (NPCIL), were at Kudankulam to see the first of the two Russian-made units attain criticality in a smooth manner.

Atomic power plant operator NPCIL is setting up two 1,000MW reactors with Russian technology and equipment at Kudankulam, around 650km from Chennai.

The over Rs170bn project, which came up in the face of intense protests in nearby villages who feared for their safety, began generating heat and steam from the 163 uranium fuel bundles loaded in the reactor.

The reactor was loaded with fuel assemblies containing about 80 tonnes of uranium oxide.

On July 11 night, armed with the AERB’s clearance, the KNPP started its journey towards criticality.

According to officials, several low power tests will be carried out in order to verify the conformance of the reactor characteristics to design objectives.

If the reports are satisfactory, the AERB will give its clearance for the next stage, which is phase-wise increase in reactor power level. At the first stage, the plant will be synchronised with the southern grid when power generation touches 400MW. That is expected to happen in 30-45 days.

After necessary regulatory clearances, power generation will be increased gradually to 50%, 75%, 90% and finally 100%. When that happens, the total installed nuclear power capacity in the country will go up to 5,780MW.

KNPP is India’s first pressurised water reactor belonging to the light water reactor category. While the power from KNPP will be shared by the southern states, the lion’s share will be for the home state Tamil Nadu, which is suffering from power deficit.

“Tamil Nadu’s share of the 1,000MW will be 463MW. As and when the power comes to our grid, it will certainly ease the power shortage to some extent,” a senior official at Tamil Nadu Generation and Distribution Corporation (Tangedco) said.

“The utility sources power from various central power generating units at varied rates but less than Rs3 per unit, whereas the power from KNPP will be over Rs3 per unit,” he said.

As for the second unit at KNPP, he said there will be time lag of six to eight months. According to Sundar, loading of dummy fuel (dummy fuel assemblies are the exact replica of the actual nuclear fuel assemblies, both in dimension and weight but without uranium) was under progress and was expected to get over in around 10 days. It is learnt construction work for the administrative building for the next two units is progressing at the KNPP site.

Sinha said it was only a matter of time before the general framework agreement was signed with the Russian suppliers for the third and fourth units. He said the total outlay for the third and fourth units would be Rs400bn.

 

 

July 14, 2013 | 09:30 PM