A closure on both directions of Bilal bin Rabah Street near Nasser bin Abdulla Al Misned Street in Al Khor will be effected from December 15.

Consequent to this, the traffic through the area will be diverted to Ibn Taimiyah Street and to the alternative local roads (as shown on the attached map). The closure is for a period of three months, Ashghal said.
Ashghal will also close a section of the service road (in both directions) on Umm Birkah Road. The closed part is located after Umm Birkah interchange for those coming from Al Thakhira and traffic will be diverted to an alternative road adjacent to the closed part. The closure will last three months starting from December 10.
With the two closures, the authorities aim to enable the works of laying sewage and treated sewage effluent rising mains of the under construction Al Thakhira Sewage Treatment Works, Transfer Pumping Station and associated pipelines project.